Current Projects Twin Cities WWTP

 

Project Location

3723 Green Point Road,

East New Market, MD 21664

Owner

Town of Secretary, MD

Engineer

ARRO Consulting

Project Value

$23,136,001


The following is a general description of the project:

Construction of a new headworks building, raw sewage pumping station, a new two-basin Sequencing Batch Reactor (SBR) process, with aerobic digesters and 24-hour storage/equalization tanks, which is prestressed post tensioned concrete structure, chemical addition facilities, conversion of chlorine contact tanks to a new UV disinfection system, a new solids dewatering system, demolition of some existing structures, upgrades to the electrical service and emergency generator set replacement.

Contract Documents Available Here